Thanks Joe,
Will an arborist report be required for the application/ permit?
If so, does the arborist need to be on any approved lists or have any specific credentials?
Thanks,
Morgan
On Tue, Dec 17, 2024 at 5:08 PM App Services <AppServices@cityoftacoma.org> wrote:
> Morgan, > > > > Thank you! That will work just fine, however there is some additional > requirements that would be needed for a Home in Tacoma review. > > > > Please see our tip sheet here: > www.tacomapermits.org/home-in-tacoma-pre-development-review > > > > *Building Details must include:* > > – Building type(s) proposed – houseplex, multiplex, rowhouse, backyard > building > – Identify which building code will be used for *each* proposed > building > – How many units will be in each building > – Drawings of the buildings showing their size, height, and appearance. > – How much of the lot will be covered by buildings (Floor Area Ratio > or FAR) > > *Site Plan must include:* > > – A scaled drawing of your lot showing property lines and building > locations. > – Any environmentally sensitive areas on the site. > – Open space and landscaping. > – Parking areas, including the number of spaces and accessibility. > – Pedestrian walkways and accessibility features. > – Location for garbage and recycling. > – Utility connections (sewer, water, power). > – How you plan to own the land (single lot, subdivided, etc.). > > > > The process is similar to our regular Pre-Development review, however the > additional detail needed is to allow our staff to provide you with the most > accurate feedback for the proposal. > > > > Please let us know if you have any questions. > > > > Thank you! > > > > > > *Joe Graff* > > Development Services Program Coordinator > > Planning & Development Services > > jgraff@cityoftacoma.org > > 253.591.5622 (rings my desk and cell) > > Tacoma Permits <www.tacomapermits.org/> | Customer Access Portal > <aca-prod.accela.com/tacoma/Default.aspx> | Customer Survey > <www.surveymonkey.com/r/JVK8QYC> > > > > *From:* Morgan Iacolucci <morganiacolucci@gmail.com> > *Sent:* Monday, December 16, 2024 2:16 PM > *To:* App Services <AppServices@cityoftacoma.org> > *Cc:* morgan@morganiacolucci.com; Costa, Patricia <PCOSTA@cityoftacoma.org > > > *Subject:* Re: Information Needed: PRE24-0193 – 1414 E Morton St > Development > > > > Thank you! > > > > The plan sets I’m planning to submit are designed according to the updated > standards set by Home in Tacoma. Will that be okay? > > > > Thanks, > > > > Morgan > > > > On Wed, Oct 16, 2024 at 9:55 AM appservices@cityoftacoma.org < > appservices@cityoftacoma.org> wrote: > > Greetings, > > More information is needed to process your pre-application request. > > > > Please confirm if you are choosing Option A review (Comment Memo Only – > $1,560) or an Option B review (Comment Memo Followed by a Virtual Meeting – > $3,120). > > > > Once all information is received, we can move forward with invoicing the > record. Pre-development fees can be credited back to the applicant if the > associated building permit is applied for within 1 year of the > pre-application request. > > > > Please feel free to contact us with any questions you might have. > > Pre-Application Requests > <urldefense.com/v3/__http:/tacomapermits.org/tip-sheet-index/pre-application-requests__;!!CRCbkf1f!T8nw5afigTwY9Cmg8b2ALB40Fyl9KUh6quIcxEZ_c6W7uMgmxv_N6aEdIqXoRnhRGGmIvGTofpI5ERhF-dTFcsGvSZcSmEhOSw$> > > > > > Thank you, > > Application Services > > > > > — > > *Morgan Iacolucci* > > c: (206) 580-8505 > > e: Morganiacolucci@gmail.com >
Will an arborist report be required for the application/ permit?
If so, does the arborist need to be on any approved lists or have any specific credentials?
Thanks,
Morgan
On Tue, Dec 17, 2024 at 5:08 PM App Services <AppServices@cityoftacoma.org> wrote:
> Morgan, > > > > Thank you! That will work just fine, however there is some additional > requirements that would be needed for a Home in Tacoma review. > > > > Please see our tip sheet here: > www.tacomapermits.org/home-in-tacoma-pre-development-review > > > > *Building Details must include:* > > – Building type(s) proposed – houseplex, multiplex, rowhouse, backyard > building > – Identify which building code will be used for *each* proposed > building > – How many units will be in each building > – Drawings of the buildings showing their size, height, and appearance. > – How much of the lot will be covered by buildings (Floor Area Ratio > or FAR) > > *Site Plan must include:* > > – A scaled drawing of your lot showing property lines and building > locations. > – Any environmentally sensitive areas on the site. > – Open space and landscaping. > – Parking areas, including the number of spaces and accessibility. > – Pedestrian walkways and accessibility features. > – Location for garbage and recycling. > – Utility connections (sewer, water, power). > – How you plan to own the land (single lot, subdivided, etc.). > > > > The process is similar to our regular Pre-Development review, however the > additional detail needed is to allow our staff to provide you with the most > accurate feedback for the proposal. > > > > Please let us know if you have any questions. > > > > Thank you! > > > > > > *Joe Graff* > > Development Services Program Coordinator > > Planning & Development Services > > jgraff@cityoftacoma.org > > 253.591.5622 (rings my desk and cell) > > Tacoma Permits <www.tacomapermits.org/> | Customer Access Portal > <aca-prod.accela.com/tacoma/Default.aspx> | Customer Survey > <www.surveymonkey.com/r/JVK8QYC> > > > > *From:* Morgan Iacolucci <morganiacolucci@gmail.com> > *Sent:* Monday, December 16, 2024 2:16 PM > *To:* App Services <AppServices@cityoftacoma.org> > *Cc:* morgan@morganiacolucci.com; Costa, Patricia <PCOSTA@cityoftacoma.org > > > *Subject:* Re: Information Needed: PRE24-0193 – 1414 E Morton St > Development > > > > Thank you! > > > > The plan sets I’m planning to submit are designed according to the updated > standards set by Home in Tacoma. Will that be okay? > > > > Thanks, > > > > Morgan > > > > On Wed, Oct 16, 2024 at 9:55 AM appservices@cityoftacoma.org < > appservices@cityoftacoma.org> wrote: > > Greetings, > > More information is needed to process your pre-application request. > > > > Please confirm if you are choosing Option A review (Comment Memo Only – > $1,560) or an Option B review (Comment Memo Followed by a Virtual Meeting – > $3,120). > > > > Once all information is received, we can move forward with invoicing the > record. Pre-development fees can be credited back to the applicant if the > associated building permit is applied for within 1 year of the > pre-application request. > > > > Please feel free to contact us with any questions you might have. > > Pre-Application Requests > <urldefense.com/v3/__http:/tacomapermits.org/tip-sheet-index/pre-application-requests__;!!CRCbkf1f!T8nw5afigTwY9Cmg8b2ALB40Fyl9KUh6quIcxEZ_c6W7uMgmxv_N6aEdIqXoRnhRGGmIvGTofpI5ERhF-dTFcsGvSZcSmEhOSw$> > > > > > Thank you, > > Application Services > > > > > — > > *Morgan Iacolucci* > > c: (206) 580-8505 > > e: Morganiacolucci@gmail.com >